Location: London, UK
Client: National Grid
Delivery Model: Design-Bid-Build
Prime Consultant: AECOM
Value: Package 2 – c. $819m CAD / Package 5 c. $128m CAD
Completion: July 2024 / January 2027
Murphy, working as part of the HOCHTIEF-MURPHY Joint Venture (HMJV), is delivering two major works packages as part of National Grid’s circa £1bn scheme to replace existing cable infrastructure which is reaching the end of its life. Package 2 comprises design and construction of approximately 33km of tunnel from Wimbledon to Crayford and eight shafts, through the full range of the London geology.
Package 5 comprises design and construction of the operational headhouses as well as associated mechanical/electrical systems. Latest milestones achieved include: